Choose your language : Lao ພາສາລາວ    English English

Logo of NRI

 

Progress Report

DateTitleHighlights
12-07-2023 Quarterly Progress Report (QR2) 2023 - Financial Progress
- List of All Subprojects
- Status of Consultant Input
- Overall Project Implementation Schedule and Updated Progress
- Grant Covenants
- GENDER ACTION PLAN (GAP) implementation
- Progress of Civil Works
- O&M of Irrigation Facilities (NRI-AF)
- WUG Establishment and Development
- Summary of WUG Establishment
- Strengthening of WUG to WUGA
- Implementation of the Agricultural Extension Activity Plan
- Crops Production Monitoring, Evaluation, and Planning
- Promotion of Clean Agriculture - Pilot Activities
- Female-focused Extension Services (FFES)
- Female Focused Extension Service (FFES) Activities
- Land Use Management Plan
- Progress of PCMPA Implementation in 4 Target Provinces
- Progress of Land Titling Implementation
25-12-2019Quarterly Progress Report (QR-3) September 2019This report is Quarterly Progress Report (QR3) July to September 2019, to be submitted to ADB on 21 October 2019.
25-12-2019Quarterly Progress Report (QR-2) June, 2019This report is Quarterly Progress Report (QR2) April to June 2019, to be submitted to ADB on 22 July 2019.
25-12-2019Quarterly Progress Report (QR-1) March, 2019This report is Quarterly Progress Report (QR1) January to March 2019, to be submitted to ADB on 22 April 2019.
25-12-2019Annual Progress Report 2018 in combination with Mid-tem Review ReportThis report is Annual Progress Report 2018 in combination with Mid-term Review Report, to be submitted to ADB on 21 January 2019.
25-12-2019Quarterly Progress Report (QR-3) September, 2018This report is the 3nd Quarterly Progress Report covering from July to September 2018, to be submitted to ADB by 20 October 2018.
25-12-2019Quarterly Progress Report (QR-2) June, 2018This report is the 2nd Quarterly Progress Report covering from April to June 2018, to be submitted to ADB by 20 July 2018.
25-12-2019Quarterly Progress Report (QR-1) March, 2018This report is the 1st Quarterly Progress Report covering from January to March 2018, to be submitted to ADB by 20 April 2018.
25-12-2019Annual Progress Report 2017This report is the 1st Annual Progress Report covering the year 2017, to be submitted to ADB by 20 January 2018.
25-12-2019Inception Report - September, 2017 Result reporting on the inspection of pesticide residues in agricultural soil, water and crops/plants and the awareness raising on pesticide in two northern provinces (Laoungnamtha and Phongsaly provinces.
10-06-2016Quarterly Progress Report - March, 2016This report is the 19th progress report covering the period from January to March 2016, to be submitted to ADB in the beginning of April 2016.
10-06-2016Annual Progress Report 2015This report is the 18th progress report covering the period from January to December 2015, to be submitted to ADB in the beginning of January 2016.
10-06-2016Quarterly Progress Report - July to September 2015This report is the 17th progress report covering the period from July to September 2015, to be submitted to ADB in the beginning of October 2015.
10-06-2016Quarterly Progress Report - April to June 2015This report is the 16th progress report covering the period from April to June 2015, to be submitted to ADB in the beginning of July 2015.
10-06-2016Quarterly Progress Report - January to March 2015This report is the 15th progress report covering the period from January to March 2015, to be submitted to ADB in the beginning of April 2015.
10-06-2016Annual Report 2015 of Project Benefit Monitoring and EvaluationAs of 31 December 2015, the overall project implementation progress is estimated at 81.0% against 80.6% of Project period of time has elapsed since the project grant effectiveness on 08 March 2011, and 79.2% elapsed compare to the project commencement on 1st August 2011.
10-06-2016Annual Progress Report 2014This report is the 4th annual progress report covering the period from January to December 2014, to be submitted to ADB in the beginning of January 2015.
10-06-2016Project Mid-Term Report - August 2011 to March 2014This progress report is the Project Mid-term Progress report to be submitted to ADB by the end of March 2014.
10-06-2016Annual Report 2014 of Project Benefit Monitoring and EvaluationAs of 31 December 2014, the overall project implementation progress is estimated at 63.8% against 63.9% of Project period of time has elapsed since the project grant effectiveness on 08 March 2011, and 61.2% elapsed compare to the project commencement on 1st August 2011.
18-07-2014Quarterly Progress Report - April to June 2014This quarterly progress report is the 11th report covering the period from April to June 2014, to be submitted to ADB in the beginning of July 2014.
18-07-2014Project Mid-Term Report - August 2011 to March 2014This progress report is the Project Mid-term Progress report to be submitted to ADB by the end of March 2014.
18-07-2014Annual Progress Report - January to December 2013This quarterly progress report is the 3rd Annual report and become to the 9th quarter report to be submitted to ADB after the Inception Workshop was organized in Vientiane on 3 August 2011 by ADB.
go to goto top
What’s News

Ministry of Agriculture and Forestry of Lao PDR    Asian Development Bank

MAF                ADB

Copyright(C) Northern Rural Infrastructure Sector Development Project Additional Financing (NRI-AF) In Lao PDR, 2011 - All Rights Reserved.