Progress Report

DateTitleHighlights
2016-06-10Quarterly Progress Report - March, 2016This report is the 19th progress report covering the period from January to March 2016, to be submitted to ADB in the beginning of April 2016.
2016-06-10Annual Progress Report 2015This report is the 18th progress report covering the period from January to December 2015, to be submitted to ADB in the beginning of January 2016.
2016-06-10Quarterly Progress Report - July to September 2015This report is the 17th progress report covering the period from July to September 2015, to be submitted to ADB in the beginning of October 2015.
2016-06-10Quarterly Progress Report - April to June 2015This report is the 16th progress report covering the period from April to June 2015, to be submitted to ADB in the beginning of July 2015.
2016-06-10Quarterly Progress Report - January to March 2015This report is the 15th progress report covering the period from January to March 2015, to be submitted to ADB in the beginning of April 2015.
2016-06-10Annual Report 2015 of Project Benefit Monitoring and EvaluationAs of 31 December 2015, the overall project implementation progress is estimated at 81.0% against 80.6% of Project period of time has elapsed since the project grant effectiveness on 08 March 2011, and 79.2% elapsed compare to the project commencement on 1st August 2011.
2016-06-10Annual Progress Report 2014This report is the 4th annual progress report covering the period from January to December 2014, to be submitted to ADB in the beginning of January 2015.
2016-06-10Project Mid-Term Report - August 2011 to March 2014This progress report is the Project Mid-term Progress report to be submitted to ADB by the end of March 2014.
2016-06-10Annual Report 2014 of Project Benefit Monitoring and EvaluationAs of 31 December 2014, the overall project implementation progress is estimated at 63.8% against 63.9% of Project period of time has elapsed since the project grant effectiveness on 08 March 2011, and 61.2% elapsed compare to the project commencement on 1st August 2011.
2014-07-18Quarterly Progress Report - April to June 2014This quarterly progress report is the 11th report covering the period from April to June 2014, to be submitted to ADB in the beginning of July 2014.
2014-07-18Project Mid-Term Report - August 2011 to March 2014This progress report is the Project Mid-term Progress report to be submitted to ADB by the end of March 2014.
2014-07-18Annual Progress Report - January to December 2013This quarterly progress report is the 3rd Annual report and become to the 9th quarter report to be submitted to ADB after the Inception Workshop was organized in Vientiane on 3 August 2011 by ADB.