Implementation Schedule

Implementation Schedule

 

The Project will be implemented for 5.5 years from August 2011 to February 2017 in phase-wise (3 Years).

YearNumber of Subproject
Component 1Component 2
Year 1

Core:2011-2014

Follow-up:2014-2017

3 subprojects, for which feasibility study has been completed during PPTA, and 6 subprojects (9 subprojects in total)9 subprojects as similar to component 1
Year 2

Core:2012-2015

Follow-up:2015-2017

9 subprojects13 subprojects
Year 3

Core:2013-2016

Follow-up:2015-2017

9 subprojects9 subprojects
Total27 subprojects31 subprojects

 

On the other hand, Component 3: Institutional Capacity Building and Component 4: Project Implementation and Management will be carried out continuously in the course of the Project from 2011 to 2017.